January 2019

The images below the site plan, and representations of the finished plant - illustrating how the design incorporates the Township's streetscape design guidelines. 

Plant Design

plant map

North view from Powell Rd.

plant design 1

Northeast view from Powell Rd.

plant design 1

East view from Powell Rd.

plant design 3
The Brush Creek Water Pollution Control Facility upgrade project construction began in July 2016 and is expected to be substantially complete by June 2019.  Currently, the Contractors are working on construction of:
 
  • Membrane Bioreactor Building and Tanks
  • Influent Pump Station
  • Master Control Building
  • Chemical Feeding Building Renovations
  • Sludge Holding Tanks
  • Backup Generator