Cranberry Township, PA - Home Page
Township Weather
Go To Search
Brush Creek Plant Upgrade
 
Water Pollution Control Facility 

Executive Summary
Introduction and Needs Assessment

The Brush Creek Water Pollution Control Facility (BWPCF) currently treats an average day flow of approximately 3.4 mgd from Cranberry Township, Marshall Township, Pine Township, and Bradford Woods Borough in Allegheny County and a small part of New Sewickley Township in Beaver County. The Brush Creek facility operates under NPDES Permit No. PA 0024571 and has a hydraulic capacity 4.5 mgd and an organic capacity of 14,000 lbs/day. The facility has a rated peak flow of 23 mgd which includes an 11.75 mgd secondary treatment by-pass (or blending). In 2011 the facility experienced a hydraulic overload and the Township entered into a Corrective Action Plan with PA DEP.

Expansion of the facility is necessary to address the CAP and hydraulic overload condition and plant capacity for future growth. Additionally, the several regulatory changes have occurred which will, in effect; reduce the capacity of the current facility.

These include the elimination of the capability to blend and mass based permit limits.

To that end, a Basis of Design was prepared for inclusion into an Act 537 Update Revision as required by the CAP. The purpose of the Act 537 Update Revision is to evaluate several alternatives for upgrades required to the Brush Creek Water Pollution Control Facility (BCWPCF).

The Basis of Design was completed in May of 2013 and is included in Exhibit 1. Analysis included in the Basis of Design, along with the Township’s current approved 537 Plan and Comprehensive plan were used to establish capacity needs. The Upgrade and Expansion Project will increase the hydraulic and organic capacity to 8.73 mgd and 19,220 lbs/d BOD5 as well as eliminate the need for blending and meet preliminary mass based limits.


           
Background

We've known since the last retooling of Cranberry's Brush Creek sewage treatment plant in 1999 that another upgrade would eventually be required to serve a growing population. Pennsylvania’s Department of Environmental Protection recently issued new requirements affecting the plant’s flow rates and associated treatment methods during peak weather events.  

In addition, tighter limits on the release of nutrients – limits which are likely to grow even more restrictive, must also be satisfied for the plant to secure its operating permits. The alternatives – each of which come with an assortment of challenges – range from $50 million for a single-phase approach, to $65 million for a two-phase approach.will be financed by a combination of higher rates for sewer system customers and increased tap-in fees.        
A step-by-step process leading to the upgrade is now underway. Construction was accelerated by a combination of new environmental requirements and a need for increased capacity. Work is expected to begin in 2015 and be completed by early 2016, according to the project engineer's timeline. Preliminary engineering, as well as work to secure state and federal operating permits, is in progress, with final engineering work slated to begin by early next year.
Brush Creek  Facility Upgrade Project

January 30, 2014 Progress Report,

presented to the Board of Supervisors


           
 
                     
  

More information on the Brush Creek Plant 

Watch the video: