Project Overview (description): The Ehrman-Garvin Connector is one of the final links in creating a connection from Route 19 to Franklin Road. This project connects Ehrman Road at its existing terminus (at the intersection of Ehrman Road and Gate Dancer Drive) to Garvin Road approximately 0.8 miles west of Franklin Road. The project consists of approximately 1,500 feet of new roadway that includes one new intersection. The project is a partnership project between Cranberry Township and Singer Construction, who is performing the earthwork and stormwater system installation as a condition of their new Mystic Ridge Development.
Project Timeline:
• Currently started
• Grading/stormwater to be completed by August 2009
• Paving to be completed by October 2009
Schedule & Restrictions:
7:00 AM – 6:00 PM – construction, periodic lane closures on Garvin Road
Contractor Information:
Singer Construction